BUILDING CONSTRUCTION DETAILS


For any questions or concerns please contact the Office of Campus Planning & Facilities at campus.facilities@lehman.cuny.edu or 718-960-8226.

Shuster Hall Library Old Gym Gillet Hall Carman Hall Music Building Campus Bridge Davis Hall


Shuster Hall

Window Replacement (Estimated Construction Time)

UPDATE: Work on the window replacements for Shuster Hall is currently delayed. Restoration work on other exterior elements of Shuster Hall continues. A return date for the third floor is not currently known.

  • Third Floor (10/10/25 – 1/23/26)
    • Some offices will move back to the Third Floor in January
  • Basement (Construction Start Delayed)
  • Second Floor (Construction Start Delayed)
  • First Floor (Construction Start Delayed)

Shuster Hall

Window Replacement
Oct-25 Nov-25 Dec-25 Jan-26 Feb-26
Third Floor  
      Basement - Construction Start Delayed
      Second Floor - Construction Start Delayed
      First Floor - Construction Start Delayed

Temporary Office Locations beginning September 29, 2025

HVAC (Air Conditioning) Replacement (Estimated Construction Time)
  • Basement/ First Floor – North and West Corridors (10/1/26 – 3/1/27)
  • Second & Third Floor – North and West Corridors (4/1/27 – 10/1/27)
  • Basement/ First Floor – South and East Corridors (11/1/27 – 3/1/28)
  • Second & Third Floor – South and East Corridors (1/1/28 – 9/1/28)

Shuster Hall

HVAC Upgrades
Oct-26 Mar-27 Apr-27 Oct-27 Nov-27 Jan-28 Mar-28 Sept-28
Basement/First Floor - North & West Corridors            
    Second/Third Floor -
North & West Corridors
       
        Basement/First Floor -
South & East Corridors
 
          Second & Third Floors -
South & East Corridors

Leonard Lief Library

Window Replacement (Estimated Construction Time)
  • Third Floor (1/26 – 2/26)
  • Second Floor (2/26 – 3/26)
  • First Floor (3/14/26 – 4/25/26)
  • Basement (3/14/26 – 4/25/26)

Leonard Lief Library

Window Replacement
Jan-26 Feb-26 March-26 April-26
Third Floor    
  Second Floor  
    First Floor
    Basement

Old Gym Building

Center for Teaching and Learning (Estimated Construction Time)

(Completed by March '26)

Window Replacement (Estimated Construction Time)

(February '26 – Summer '28)

Old Gym Building

Construction Projects
Oct-25 Feb-26 Mar-26 Aug-28
Center for Teaching & Learning
  Window Replacement

Carman Hall

Carman Hall Projects
  • Plaza Roof Replacement (Complete by January '26)
  • West Main Staircase/Entrance Rebuild (Complete by February '26)
  • East Main Staircase/Entrance Rebuild (February '26 - June '26)
  • Terraces Rebuild (Nov '25 – August '26)
  • Bathroom Accessibility Improvements (January '26 - May '27)
  • HVAC Upgrade (June '26 - June '29)

Carman Hall

Construction Projects
Oct-25 Nov-25 Jan-26 Feb-26 May-26 June-26 Aug-26 Nov-26 May-27 June-29
Plaza Roof              
West Staircase/Entrance            
      East Staircase/Entrance      
  Terraces      
    Bathrooms
          HVAC

Music Building

Facade Work / Copper Roof Refurbishment (Estimated Construction Time)

(7/5/25 – 8/1/26)

Music Building

Facade and Roof Repair
Oct-25 Jan-26 August-26
Facade Work
Copper Roof Refurbishment

Campus Bridge

Structural Restoration (Estimated Construction Time)

(Jan '26 – Winter '26)

Campus Bridge

Structural Restoration
Jan-26 June-26 Dec-26
Repair and Restoration

Davis Hall

Roof Replacement (Estimated Construction Time)

(7/5/25 – 8/1/26)

COMPLETED

Social Work Moving in January '26.

Davis Hall

Construction Projects
Jun-25 Dec-25 Jan-26
Roof Replacement
Social Work Department

Gillet Hall

Roof Replacement (Estimated Construction Time)

(9/5/25 – 12/20/25)

COMPLETED

Gillet Hall

Roof Replacement
Oct-25 Nov-25 Dec-25
Roof Replacement