BUILDING CONSTRUCTION DETAILS


For any questions or concerns please contact the Office of Campus Planning & Facilities at campus.facilities@lehman.cuny.edu or 718-960-8226.

Shuster Hall Library Old Gym Gillet Hall Carman Hall Music Building Campus Bridge Davis Hall


Shuster Hall

Window Replacement (Estimated Construction Time)

UPDATE: Work on the window replacements for Shuster Hall is currently delayed. Restoration work on other exterior elements of Shuster Hall continues. Several offices have returned to Shuster, with some moving to new spaces and others to different buildings.

  • The offices of the President (350), Provost (379), and Administration and Finance (355) are back in their regular spaces.
  • Enrollment Management is remaining in 152.
  • Academic Personnel is now in 301.
  • Strategic Planning, Assessment, and Institutional Research (SPAIR) is in 359.
  • Campus Planning and Facilities is in Building T3, rooms 219, 221A, and 221B.
  • Institutional Advancement - TBD
  • Research Administration, Compliance, Learning, and Enhancement (ORACLE) remains remote.

Shuster Hall

Window Replacement
Oct-25 Nov-25 Dec-25 Jan-26 Feb-26
Third Floor  
      Basement - Construction Start Delayed
      Second Floor - Construction Start Delayed
      First Floor - Construction Start Delayed

HVAC (Air Conditioning) Replacement (Estimated Construction Time)
  • Basement/ First Floor – North and West Corridors (10/1/26 – 3/1/27)
  • Second & Third Floor – North and West Corridors (4/1/27 – 10/1/27)
  • Basement/ First Floor – South and East Corridors (11/1/27 – 3/1/28)
  • Second & Third Floor – South and East Corridors (1/1/28 – 9/1/28)

Shuster Hall

HVAC Upgrades
Oct-26 Mar-27 Apr-27 Oct-27 Nov-27 Jan-28 Mar-28 Sept-28
Basement/First Floor - North & West Corridors            
    Second/Third Floor -
North & West Corridors
       
        Basement/First Floor -
South & East Corridors
 
          Second & Third Floors -
South & East Corridors

Leonard Lief Library

Window Replacement (Estimated Construction Time)
  • Third Floor (1/26 – 2/26)
  • Second Floor (2/26 – 3/26)
  • First Floor (3/14/26 – 4/25/26)
  • Basement (3/14/26 – 4/25/26)

Leonard Lief Library

Window Replacement
Jan-26 Feb-26 March-26 April-26
Third Floor    
  Second Floor  
    First Floor
    Basement

Old Gym Building

Center for Teaching and Learning (Estimated Construction Time)

(Completed by March '26)

Window Replacement (Estimated Construction Time)

(February '26 – Summer '28)

Old Gym Building

Construction Projects
Oct-25 Feb-26 Mar-26 Aug-28
Center for Teaching & Learning
  Window Replacement

Carman Hall

Carman Hall Projects
  • Plaza Roof Replacement (Complete by January '26)
  • West Main Staircase/Entrance Rebuild (Complete by February '26)
  • East Main Staircase/Entrance Rebuild (February '26 - June '26)
  • Terraces Rebuild (Nov '25 – August '26)
  • Bathroom Accessibility Improvements (January '26 - May '27)
  • HVAC Upgrade (June '26 - June '29)

Carman Hall

Construction Projects
Oct-25 Nov-25 Jan-26 Feb-26 May-26 June-26 Aug-26 Nov-26 May-27 June-29
Plaza Roof              
West Staircase/Entrance            
      East Staircase/Entrance      
  Terraces      
    Bathrooms
          HVAC

Music Building

Facade Work / Copper Roof Refurbishment (Estimated Construction Time)

(7/5/25 – 8/1/26)

Music Building

Facade and Roof Repair
Oct-25 Jan-26 August-26
Facade Work
Copper Roof Refurbishment

Campus Bridge

Structural Restoration (Estimated Construction Time)

(Jan '26 – Winter '26)

Campus Bridge

Structural Restoration
Jan-26 June-26 Dec-26
Repair and Restoration

Davis Hall

Roof Replacement (Estimated Construction Time)

(7/5/25 – 8/1/26)

COMPLETED

Social Work Moving in January '26.

Davis Hall

Construction Projects
Jun-25 Dec-25 Jan-26
Roof Replacement
Social Work Department

Gillet Hall

Roof Replacement (Estimated Construction Time)

(9/5/25 – 12/20/25)

COMPLETED

Gillet Hall

Roof Replacement
Oct-25 Nov-25 Dec-25
Roof Replacement