BUILDING CONSTRUCTION DETAILS
For any questions or concerns please contact the Office of Campus Planning & Facilities at campus.facilities@lehman.cuny.edu or 718-960-8226.
Shuster Hall Library Old Gym Gillet Hall Carman Hall Music Building Campus Bridge Davis Hall
Shuster Hall
Window Replacement (Estimated Construction Time)
UPDATE: Work on the window replacements for Shuster Hall is currently delayed. Restoration work on other exterior elements of Shuster Hall continues. Several offices have returned to Shuster, with some moving to new spaces and others to different buildings.
- The offices of the President (350), Provost (379), and Administration and Finance (355) are back in their regular spaces.
- Enrollment Management is remaining in 152.
- Academic Personnel is now in 301.
- Strategic Planning, Assessment, and Institutional Research (SPAIR) is in 359.
- Campus Planning and Facilities is in Building T3, rooms 219, 221A, and 221B.
- Institutional Advancement - TBD
- Research Administration, Compliance, Learning, and Enhancement (ORACLE) remains remote.
Shuster Hall |
||||
|---|---|---|---|---|
Window Replacement |
||||
| Oct-25 | Nov-25 | Dec-25 | Jan-26 | Feb-26 |
| Third Floor | ||||
| Basement - Construction Start Delayed | ||||
| Second Floor - Construction Start Delayed | ||||
| First Floor - Construction Start Delayed | ||||
HVAC (Air Conditioning) Replacement (Estimated Construction Time)
- Basement/ First Floor – North and West Corridors (10/1/26 – 3/1/27)
- Second & Third Floor – North and West Corridors (4/1/27 – 10/1/27)
- Basement/ First Floor – South and East Corridors (11/1/27 – 3/1/28)
- Second & Third Floor – South and East Corridors (1/1/28 – 9/1/28)
Shuster Hall |
|||||||
|---|---|---|---|---|---|---|---|
HVAC Upgrades |
|||||||
| Oct-26 | Mar-27 | Apr-27 | Oct-27 | Nov-27 | Jan-28 | Mar-28 | Sept-28 |
| Basement/First Floor - North & West Corridors | |||||||
| Second/Third Floor - North & West Corridors |
|||||||
| Basement/First Floor - South & East Corridors |
|||||||
| Second & Third Floors - South & East Corridors |
|||||||
Leonard Lief Library
Window Replacement (Estimated Construction Time)
- Third Floor (1/26 – 2/26)
- Second Floor (2/26 – 3/26)
- First Floor (3/14/26 – 4/25/26)
- Basement (3/14/26 – 4/25/26)
Leonard Lief Library |
|||
|---|---|---|---|
Window Replacement |
|||
| Jan-26 | Feb-26 | March-26 | April-26 |
| Third Floor | |||
| Second Floor | |||
| First Floor | |||
| Basement | |||
Old Gym Building
Center for Teaching and Learning (Estimated Construction Time)
(Completed by March '26)
Window Replacement (Estimated Construction Time)
(February '26 – Summer '28)
Old Gym Building |
|||
|---|---|---|---|
Construction Projects |
|||
| Oct-25 | Feb-26 | Mar-26 | Aug-28 |
| Center for Teaching & Learning | |||
| Window Replacement | |||
Carman Hall
Carman Hall Projects
- Plaza Roof Replacement (Complete by January '26)
- West Main Staircase/Entrance Rebuild (Complete by February '26)
- East Main Staircase/Entrance Rebuild (February '26 - June '26)
- Terraces Rebuild (Nov '25 – August '26)
- Bathroom Accessibility Improvements (January '26 - May '27)
- HVAC Upgrade (June '26 - June '29)
Carman Hall |
||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
Construction Projects |
||||||||||||
| Oct-25 | Nov-25 | Jan-26 | Feb-26 | May-26 | June-26 | Aug-26 | Nov-26 | May-27 | June-29 | |||
| Plaza Roof | ||||||||||||
| West Staircase/Entrance | ||||||||||||
| East Staircase/Entrance | ||||||||||||
| Terraces | ||||||||||||
| Bathrooms | ||||||||||||
| HVAC | ||||||||||||
Music Building
Facade Work / Copper Roof Refurbishment (Estimated Construction Time)
(7/5/25 – 8/1/26)
Music Building |
||
|---|---|---|
Facade and Roof Repair |
||
| Oct-25 | Jan-26 | August-26 |
| Facade Work | ||
| Copper Roof Refurbishment | ||
Campus Bridge
Structural Restoration (Estimated Construction Time)
(Jan '26 – Winter '26)
Campus Bridge |
||
|---|---|---|
Structural Restoration |
||
| Jan-26 | June-26 | Dec-26 |
| Repair and Restoration | ||
Davis Hall
Roof Replacement (Estimated Construction Time)
(7/5/25 – 8/1/26)
COMPLETED
Social Work Moving in January '26.
Davis Hall |
||
|---|---|---|
Construction Projects |
||
| Jun-25 | Dec-25 | Jan-26 |
| Roof Replacement | ||
| Social Work Department | ||
Gillet Hall
Roof Replacement (Estimated Construction Time)
(9/5/25 – 12/20/25)
COMPLETED
Gillet Hall |
||
|---|---|---|
Roof Replacement |
||
| Oct-25 | Nov-25 | Dec-25 |
| Roof Replacement | ||
-